Table T1. Expedition 307 operations plan and time estimates.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Transit ~300 nmi to Site PORC-04A @ 10.5 kt
|
28.6 h
|
|
|
|
|
|
|
Hole A: APC to refusal @ ~75 mbsf, XCB to 112 mbsf, 4 temp. meas.
|
|
|
|
Wireline log with triple combo & FMS-sonic (12.0 h)
|
|
|
|
Hole B: APC to refusal @ ~75 mbsf, XCB to 112 mbsf
|
|
|
|
Hole C: APC to refusal @ ~75 mbsf, XCB to 112 mbsf
|
|
|
|
|
|
|
|
|
|
|
|
Transit ~0.5 nmi to Site PORC-03A @ 10.5 kt
|
|
|
|
|
|
|
|
Hole A: APC to refusal @ ~75 mbsf, XCB to 220 mbsf, 4 temp. meas.
|
|
|
|
Wireline log with triple combo/FMS-sonic/VSP (WST) (18.0 h)
|
|
|
|
Hole B: APC to refusal @ ~75 mbsf, XCB to 220 mbsf
|
|
|
|
Hole C: APC to refusal @ ~75 mbsf, XCB to 220 mbsf
|
|
|
|
|
|
|
|
|
|
|
|
Transit ~7 nmi to Site PORC-02A @ 10.5 kt
|
|
|
|
|
|
|
|
Hole A: APC to refusal @ ~75 mbsf, XCB to 200 mbsf, 4 temp. meas.
|
|
|
|
Wireline log with triple combo & FMS-sonic (11.25 h)
|
|
|
|
Hole B: APC to refusal @ ~75 mbsf, XCB to 200 mbsf
|
|
|
|
|
|
|
|
|
|
|
|
Transit ~1035 nmi to Ponta Delgado @ 10.5 kt
|
|
|
|
|
|
Discharge Expedition 307 Science Party
|
|
|
|
|
|
|
|
Transit ~3525 nmi to Mobile @ 10.5 kt
|
|
|
|
|
|
End of Expedition 307
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total length of expedition including port call(s):
|
|
Notes: Seafloor depth is prospectus water depth plus 11.0 m adjustment from waterline to rig floor (i.e., drillers depth). Advanced piston corer (APC) refusal depths are arbitrary. APC coring will proceed as deep as possible if justified by core quality/quantity. Use of the extended core barrel (XCB) will be dependent upon results of APC coring. Temperature measurements for formation gradient will be used primarily for hydrocarbon safety control. FMS = Formation MicroScanner, VSP = vertical seismic profile, WST = water sampling temperature probe.