Operations description (mbsf)
|
|
|
|
|
|
Transit 448 nmi at 10.5 kt to Site BT4-4A
|
1.8
|
|
|
BT4-4A
|
27.26628°N,
94.40316°W
|
1435
|
Hole A: APC/XCB core to 230 mbsf; fill hole with heavy mud (includes 3 APCT and 1 DVTPP measurements, plus 2 T2P deployments).
|
|
1.6
|
|
Normal Pressure Brazos-Trinity Basin flank E. Breaks Blk. 735
|
|
|
|
Move 2.5 nmi at 1.5 kt in DP mode to Site BT4-2A
|
0.1
|
|
|
BT4-2A
|
27.30136°N,
94.38754°W
|
1476
|
Hole A: APC/XCB core to 340 mbsf; fill hole with heavy mud (includes 3 APCT and 1 DVTPP measurements, plus 2 T2P deployments).
|
|
1.8
|
|
Normal Pressure Brazos-Trinity Basin center E. Breaks Blk. 692
|
Wireline logging (including hole preparation): - Triple combo/FMS-sonic/VSP (20 m stations/5 min per station)
|
|
|
1.5
|
Hole B: MWD at 25 m/h ROP to 340 mbsf; fill hole with heavy mud.
|
|
|
1.1
|
|
|
|
Move 2.5 nmi at 1.5 kt in DP mode to Site BT4-4A
|
0.1
|
|
|
BT4-4A
|
27.26628°N,
94.40316°W
|
1435
|
Hole B: MWD at 25 m/h ROP to 230 mbsf; fill hole with heavy mud.
|
|
|
0.9
|
|
|
|
Transit 283 nmi at 10.5 kt to Site URS-3C
|
1.1
|
|
|
URS-3C
|
28.09938°N,
89.02520°W
|
1321
|
Hole A: MWD at 25 m/h ROP to 238 mbsf; fill hole with heavy mud. Top of "Blue" sand projected at 258 mbsf
|
|
|
0.9
|
|
|
|
Move 3.4 nmi at 1.5 kt in DP mode to Site URS-2C
|
0.1
|
|
|
URS-2C
|
28.09124°N,
89.07252°W
|
1262
|
Hole A: MWD at 25 m/h ROP to 358 mbsf; fill hole with heavy mud. Top of "Blue" sand projected at 378 mbsf
|
|
|
1.1
|
|
|
|
Move 3.4 nmi at 1.5 kt in DP mode to Site URS-1B
|
0.1
|
|
|
URS-1B
|
28.07974°N,
89.13931°W
|
1057
|
Hole A: MWD at 25 m/h ROP to 612 mbsf; fill hole with heavy mud. Top of "Blue" sand projected at 632 mbsf
|
|
|
1.1
|
Abnormal Pressure Mars-Ursa Basin Miss.Canyon Blk. 897
|
Rendezvous with work boat to offload MWD tools
|
0.1
|
|
|
Hole B: APC/XCB core to 612 mbsf; fill hole with heavy mud (includes 3 APCT and 1 DVTPP measurements)
|
|
3.2
|
|
|
|
|
- Wireline logging (including hole preparation): Triple combo/FMS-sonic/VSP (20 m stations/5 min per station)
|
|
|
1.5
|
|
|
|
Hole C: Drill; 5 T2P deployments plus allowance for 5 APC half-cores. Fill hole with heavy mud.
Note: Core with heavy mud from 481 mbsf to TD (last 130 m).
Top of "Blue" sand projected at 632 mbsf
|
|
1.7
|
|
|
|
|
Move 3.4 nmi at 1.5 kt in DP mode to Site URS-2C
|
0.1
|
|
|
URS-2C
|
28.09124°N,
89.07252°W
|
1262
|
Hole B: APC/XCB core to 358 mbsf; fill hole with heavy mud (includes 3 APCT and 1 DVTPP measurements)
|
|
1.5
|
|
Abnormal Pressure Mars-Ursa Basin Miss.Canyon Blk. 899
|
Hole C: Drill; 5 T2P deployments plus allowance for 5 APC half-cores. Fill hole with heavy mud.
Note: Core with heavy mud from 328 mbsf to TD (last 30 m).
Top of "Blue" sand projected at 378 mbsf
|
|
1.6
|
|
|
|
|
Move 3.4 nmi at 1.5 kt in DP mode to Site URS-3C
|
0.1
|
|
|
URS-3C
|
28.09938°N,
89.02520°W
|
1321
|
Hole B: APC/XCB core to 238 mbsf; fill hole with heavy mud (includes 3 APCT and 1 DVTPP measurements, plus 1 T2P deployment).
Top of "Blue" sand projected at 258 mbsf
|
|
1.4
|
|
Abnormal Pressure Mars-Ursa Basin Miss.Canyon Blk. 855
|
|
|
Transit 1374 nmi T 10.5 kt to Balboa, Panama thorough Canal
|
6.5
|
|
|
|
|
|
|
10.1
|
12.8
|
8.1
|
|
|
|
|
31.0
|
|
|