Site U1362 | Site 1027 | Site U1363
IODP Expedition 327: Juan de Fuca Ridge-Flank Hydrogeology
Site U1301 Summary
PDF file is available for download.
24 August 2010
Background
Expedition 301 returned to the Juan de Fuca area and drilled deeper into
basement, sampled additional sediment, basalt, and microbiological materials,
replaced the borehole observatory in Hole 1026B, and established two additional
CORK observatories at Site U1301 for use in long-term three-dimensional
hydrogeologic experiments (Fisher, Urabe, Klaus, et al., 2005). One of the
primary objectives of this expedition was to recover the CORK instrument string
deployed in Hole U1301B, which researchers were unable to recover during
submersible operations in the summer of 2009 because it was being held at
depth, and deploy a replacement instrument string. Depending on the length of
the recovered string and the space available in the CORK, we were prepared to
deploy a new string that included thermal sensors, fluid samplers, and
microbial growth experiments.
Operations
Following
operations at Hole U1362A, the ship offset in dynamic positioning mode to Hole
U1301B, 800 m to the south-southwest. A
new bottom-hole assembly (BHA) that included the CORK recovery tool was made up
and tripped to the seafloor by 1615 hr on 17 August. At 1730 hr the recovery
tool engaged the Hole U1301B CORK head but before the J-tool could be engaged
the recovery tool heaved off. This required a second engagement attempt and by
1815 hr the tool was back on the CORK head. Engagement of the J-slot tool was
ineffectual so 10,000 lbs weight was applied to the top of the CORK, allowing
us to proceed with string recovery operations. It was subsequently determined
that the CORK recovery tool used for these operations was incompatible with the
wellhead on the Hole U1301B CORK, which has long lugs that prevented engagement
of the J-slot. Fortunately, we were able to complete subsequent string recovery
and deployment operations despite having the wrong CORK recovery tool on the
drill string. The sinker bars were lowered
and after multiple attempts the GS overshot engaged the instrument string top
plug. Although tension was applied to the instrument string, the instrument
string appeared to be stuck in place, as had been found during the Summer 2009 Atlantis operations. After working the sandline with various
amounts of overpull the instrument string either stretched or creeped by
several meters upward. At 0920 hr on 17 August the instrument string parted.
The CORK recovery tool was disengaged and a portion of the instrument string
was recovered back to the surface. Upon recovery it was found that a splice in
the Spectra rope had failed directly above the middle plug of the installed
instrument string. Five temperature data loggers and 377 m of Spectra rope were
recovered. After laying out the recovered portion of the instrument string the
CORK head was re-engaged at 2225 hr. Another sandline run was made to log the
inside of the CORK using an autonomous temperature logger to obtain a
temperature profile (indicating conditions in the surrounding hole) and to
determine the depth of the available open hole for new instruments. This
allowed proper configuration of the replacement instrument string. The logging
tool was stopped for 5 minutes at 5 m increments in the upper 50 m of the CORK,
and subsequently at 25 m intervals. The bottom of the open CORK casing was
tagged at 3037 m (370 m below seafloor). The recovery tool was disengaged once
again at 0130 hr on 18 August. Make-up of the replacement instrument string
began at 0145 hr. This included the rigging of the Schlumberger electric
logging line. The new Electronic Release System (ERS), under development by
Stress Engineering for use with the developmental SCIMPI CORK system, was used
for this deployment since the Hole U1301B CORK system was not configured with
an instrument string latch-down system. Historically there have been a lot of
problems jarring off the instrument string without dislodging the upper
landing/seal sub. Therefore it was hoped that the ERS system would work. The
replacement instrument string, which included three thermistor probes and
extended to a depth of ~50 mbsf, was ready for deployment at 0330 hr and the
CORK running tool was engaged once again at 0435 hr. The instrument string was
successfully landed and released using the ERS without incident and the
Schlumberger logging line was recovered and rigged down. At 0530 hr on 18
August the CORK recovery tool was disengaged, ending operations at Hole U1301B.
Science Results
Of the five autonomous temperature loggers deployed in
Hole U1301B on Expedition 301, one would communicate and download data. This is
not surprising, as all of the tools were deployed well beyond their intended
4-5 year battery life. The four tools that would not wake up are to be returned
to the manufacturer for servicing and data download (data are stored in
nonvolatile memory). The one tool that did respond and provided data shows that
temperatures at depth began to rise beginning in Summer 2009, soon after
cementing on Expedition 321T. In addition, the temperature log collected in the
upper 370 m of the open CORK casing shows that the thermal gradient in Hole
1301B has nearly returned to a pre-drilling state. Collectively, these data
suggest that the remedial cementing conducted in Summer 2009 on Expedition 321T
was successful in sealing the hole.
References
Fisher, A.T., Urabe, T., Klaus, A., and the Expedition 301 Scientists, 2005. Proc. IODP, 301: College Station, TX (Integrated
Ocean Drilling Program Management International, Inc.). doi:10.2204/iodp.proc.301.2005
|