< Previous week | Next week >
IODP Expedition 327: Juan de Fuca Ridge-Flank Hydrogeology
Week 2 Report (12-18 July 2010)
PDF file is available for download.
19 July 2010
Operations
Hole U1362A
The first stage of operations
for Hole U1362A consisted of deploying a reentry cone with 20 inch conductor
casing attached, drilling a hole a few meters into basement, and then cementing
a string of 16 inch casing to isolate the sediment column above the basement.
Based on the results of the jet in test conducted last week, a 53 m string of
20 inch casing was made up and latched into a reentry cone. The reentry cone
was deployed through the moonpool at 1700 hr on 12 July 2010 and Hole U1362A
(prospectus Site SR-2A) was spudded at 2345 hr that day. The cone reached the
seafloor at 1100 hr on 13 July. The drilling bottom-hole assembly (BHA) was
assembled using a 18-1/2" tri-cone drill bit and an under reamer with its
cutters set to a maximum diameter of 21.5 inches. The drill string was lowered
to the seafloor and the reentry cone was reentered at 0245 hr. After drilling
for 17 h at an average rate of penetration (ROP) of 18 m/hr, the hole was
terminated at 2913 m below rig floor (mbrf) or 241 m below seafloor (mbsf). The
hole was cleaned with repeated mud sweeps and the drill string was pulled out
of the hole at 0920 hr on 15 July. The depth of the basement contact was
inferred to be at 2908 mbrf (236 mbsf). Frequent referral to the tide tables
for this time period contributed to keeping the drilling depths consistent as
throughout our time on site the tidal fluctuation resulted in a 3 m change of
the sea level reference datum used by the driller. The rig floor was prepared
for running casing and by 1415 hr on 15 July ~230 m of 16 inch casing was
assembled with each joint being welded together. Once the casing running tool
was attached, the casing was lowered to the seafloor, and Hole U1362A was
reentered for a second time. The casing hanger was landed at 2315 hr with the
casing shoe at 230 mbsf, ~6 m above the basement contact. The bottom of the
hole was cemented with 42 barrels of cement pre-blended with Cello Flake and a
1.6% by volume calcium chloride accelerator. The drill string cleared the rig
floor at 0930 hr on 16 July, ending the initial stage of operations at Hole
U1362A.
Hole U1362B
The first stage of operations
at Hole U1362B was identical to Hole U1362A. An identical 53 m string of 20
inch casing was made up and latched into another reentry cone. Hole U1362B
(prospectus Site SR-2B) was spudded at 2135 hr on 16 July. The cone reached the
seafloor at 1005 hr on 17 July. The drilling BHA was assembled as before, the
drill string was lowered to the seafloor and the reentry cone was reentered at
0056 hr on 18 July. Drilling commenced at 0230 hr and continued until 1700 hr
at an ROP of 25 m/hr. The hole was terminated at 2922 mbrf or 250 mbsf, with
the basement contact inferred at 242 mbsf. The hole was cleaned with repeated
mud sweeps and the drill string trip back to the surface was initiated at 2245
hr on 18 July. The Ocean Ranger
arrived at 0715 hr while the drilling process was underway. This 117 ft long
seagoing tug came alongside the port side at 0730 hr and all cargo (completion
packers, CORK components, lab supplies, and some food) was transferred along
with three Transocean crew members. The Ocean Ranger
Science Results
Scientific laboratory training and outreach activities dominated the second week of the expedition. An orientation was given on sampling policy, SampleMaster, and core flow. Mid-week, upper oceanic crust material was recovered from the bit during drilling operations at Hole U1362A. A science meeting was held to discuss the shipboard and shore-based sampling strategy for this material. The petrologists started describing legacy
core from Leg 168 holes in this region, worked on finalizing the core
description template, and described the material recovered from the drill bit. The physical properties team has been training on the thermal conductivity,
pycnometer, and P-wave
velocity instruments. The outreach officers were trained on the digital imaging
track and commenced imaging Leg 168 cores. The CORK specialists continued
preparing their equipment for deployment. Science
teams handed in the first draft of their laboratory methods for review.
The engineering staff and CORK specialists completed all plumbing
that was possible with the CORKs in their current position on the deck. Lines
were pressure tested and a few leaks were fixed. The engineers are in the
process of organizing the cargo delivered by the Ocean Ranger.
Outreach
The weekly outreach curriculum continued with "Drilling, Coring,
Logging, and CORKing," a multi-day DarcyÕs Law experiment, a presentation on
Osmosamplers (osmotically driven fluid samplers) and associated experiments,
illustration classes, an introduction to IODP databases, training on how to
record audio podcasts, and a reading assignment on "How People Learn" published
by the National Research Council.
Technical Support and HSE Activities
HSE activities
The weekly fire and boat drill was held as scheduled.
Laboratory activities:
Technical staff continues to
provide support for various science, education and engineering projects.
Ongoing lab projects include the following: Internet Cafe remodeling: old
carpet removed, new flooring installed, and new book shelves being built;
section half multisensor logger hardware upgrade project: hardware installation
completed, motion control hardware testing begun; whole core multisensor logger
software upgrade project continues; moisture and density/pycnometer software
upgrade project: meetings held to discuss user and database interface;
installation of the reverse osmosis water tank in the chemistry lab completed;
installation of the analytical gas monitoring system completed and tested;
refurbishment of interstitial water squeezers: press stands disassembled for
sand blasting and painting.
|