IODP Expedition 328: Cascadia A-CORK Observatory
Site U1364 Summary
PDF file is available for download.
The operational objective of Expedition 328 was the
installation of a new permanent hydrologic borehole observatory near Ocean
Drilling Program Site 889. The format of the new installation followed the
Advanced CORK (ACORK) design, which will facilitate pressure monitoring at
multiple formation levels on the outside of a 10-3/4 inch casing string.
The casing is sealed at the bottom, leaving the inside available for future installation
of additional monitoring instruments. The successful installation of the
observatory will allow documentation of the average state of pressure in
the frontal part of the Cascadia accretionary prism, the pressure
gradients driving flow from the consolidating sediments, the mode of formation
of gas hydrates, the influence of gas hydrates and free gas on the mechanical
properties of their host lithology, the response of the material to seismic
ground motion, and the magnitude of strain at the site caused by episodic
seismic and aseismic slip in this subduction setting. At a later date, the
observatory will be connected to the NEPTUNE fiber-optic cable for power and
real-time communications from land.
Expedition 328 began at 0836 hr on 5 September 2010 when the
first line was passed ashore at Ogden Point Pier A in Victoria, B.C. After
completing port call public relations, logistical, and maintenance activities,
we departed Victoria for Site U1364 (CAS-01CORK) when the last line was
released at 1606 hr on 9 September. After maneuvering away from the pier, the
vessel began the 145 nmi transit to the site at 1700 hr. The ship arrived on
location at 0600 hr on 10 September concluding a transit that averaged 11.2
knots.
Our first objective was to perform a jet-in test to verify
the water depth and establish the conductor casing length to be deployed with
the re-entry cone, followed by jetting in the casing and re-entry cone. The
Vibration Isolated Television (VIT) was deployed to observe the bit contacting
the seafloor at 1329.0 m below rig floor (mbrf), and the jet-in test was
conducted reaching 55 m below seafloor (mbsf). Based on this result, the
conductor casing was assembled consisting of 3 joints of 16 inch casing and a
casing shoe joint for a total length of 53 m, which was latched into a standard
re-entry cone. Once the drilling bottom hole assembly (BHA) equipped with a 117/16
inch APC/XCB bit was latched into the casing hanger, the reentry cone was
deployed and the jetting of the reentry cone and casing was initiated at 0600
hr on 12 September while being monitored via the VIT. The 53 m assembly was
jetted in and landed by1435 hr and the drill string was tripped back to the rig
floor.
After jetting in the 16 inch casing and re-entry cone, our
next objective was to drill a 14-3/4 inch hole to accommodate the
10-3/4 inch casing string. A drilling BHA with a 14-3/4 drilling bit
was made up and deployed, reentering Hole U1364A at 0905 hr on 13 September.
The VIT was recovered and then drilling advancing without incident to a final
depth of 336.0 mbsf. High viscosity mud sweeps (20 barrels (bbl) each) were
circulated at 164, 193, 222, 278, 307, and at 336.0 mbsf. A large high
viscosity 50 bbl flush was pumped at the conclusion of drilling. The hole was
then displaced with 250 bbl of 10.5 pounds/gallon (ppg) mud. The drill string
was recovered with the bit clearing the rotary table at 1435 hr on 14
September.
The next operational step was to make up the ACORK assembly.
The construction of the ACORK, which include making connections to the
hardware, strapping and taping the umbilical to the casing, and making the
plumbing connections to the screens and ACORK, began at 1430 hr on 14 September
and continued to 1000 hr on 15 September. The ACORK assembly included a custom
ACORK head, a 10-3/4 inch casing hanger, 20 joints of 10-3/4 inch
casing, 2 pup joints of 10-3/4 inch casing, a TAM Freecap 10 inch x 14 inch
dual-element swellable packer, and 4 screen joints of 10-3/4 inch casing
and one shoe joint. The length of the entire assembly was 329.1 m. Because 6.0
m of ACORK head extended above the hang-off point in the reentry cone, the
effective depth of the assembly into the hole was 323.1 m. With a 12.9 m rat
hole, the bottom of the hole was 336.0 mbsf. The next phase was making up a
reaming BHA, which included a 9-7/8 inch tricone bit, a
9.5 inch HOC DTU950 under-reamer, a 9.5 inch Ultra XL mud motor, and the CADA
casing running tool. The total length of this BHA was 418.9 m. As the BHA was
being assembled, it was lowered incrementally into the ACORK suspended in the
moon pool until the running tool landed into the ACORK at 1345 hr on 15
September. The ACORK and reaming assembly were then lowered into the water with
the ACORK head ~10 m beneath the surface for 5 minutes to purge any entrapped
air. Once the ACORK head was back in the moon pool, the four purge valves were
manually turned to the closed position. The ACORK and reaming BHA were deployed
and Hole U1364A was entered for the second time at 1930 hr. The ACORK
was gradually lowered into the open hole until it was successfully landed in
the reentry cone at 0025 hr on 16 September. No under-reaming was required,
because the hole appeared to have remained open, possibly due to the presence
of the 10.5 ppg mud that was pumped into the hole at the conclusion of the
drilling process.
The ROV platform was tethered to the VIT and deployed at
0400 hr on 16 September. The platform was successfully deployed when the
mechanical release activated upon contacting the CADA top hat at 0515 hr. The
VIT was then recovered.
A Hammer Drill System (HDS) cone, adapted to fit over the 16
inch casing hanger at the top of the ACORK to facilitate re-entry, was made up
and free fall deployed at 0820 hr on 16 September. However, the cone was
dislodged while retrieving the drill string and fell to the seafloor. The
drilling string was tripped back to the rig floor.
The final operation was deployment of a hydraulic packer to
seal the bottom of the 10-3/4 inch casing. The packer assembly was deployed
and Hole U1364A was reentered for the third time at 2320 hr on 16 September.
Although the 16 inch casing hanger presented a smaller target than the HDS
cone, the reentry was made in less than an hour. The packer was positioned at
319 mbsf or 4 m above the casing shoe with a circulating head in place. Prior
to activating the packer, the inside of the casing was displaced with one
volume of seawater while maintaining pressure below 200 psi to insure that the
packer would not inflate prematurely. At 0230 hr the activating steel ball was
dropped into the pipe and seated inside the bridge plug. The pressure was
gradually increased until the packer set at ~1300-1400 psi. The packer was
released at 0335 hr when ~2700 psi was applied. The driller pulled back in the hole, circulated seawater while
waiting for the cement to be mixed, and then pumped ~4 bbl of 16 ppg cement
covering the packer with ~14 m of cement. The inside of the casing was then
flushed with 3 volumes of seawater. At 0600 hr, the driller began to recover
the drill string, which was back onboard at 1400 hr, ending operations at Site
U1364.
The ship was secured for transit, the thrusters raised and
the ship departed for port. The JR arrived at Esquimalt Graving Dock in
Victoria B.C. at 0800 hr on 18 September 2010, concluding Expedition 328.
|