Next week >
IODP Expedition 336: Mid-Atlantic Ridge Microbiology
Week 1 Report (15-24 September 2011)
PDF file is available for download.
The first week of IODP Mid-Atlantic Microbiology Expedition
(336) consisted of a very short port call in Barbados, the transit to the North
Pond area on the flank of the Mid-Atlantic Ridge, and the retrieval of the
existing CORK observatory from Hole 395A.
Science Results
The primary science objective of
IODP Expedition 336 is to investigate the nature of the subseafloor deep
biosphere in oceanic crust and overlying sediments. The upper ~500 m of igneous
ocean crust is fractured and permeable, harboring the largest hydrologically
active aquifer on Earth. We know that microbes inhabit this aquifer, and we
also know that microbes are abundant and play active roles in rock alteration
of exposed outcrops at the seafloor. However, we do not know the extent of
microbial colonization in the subseafloor, the diversity and activity of this
crustal biome, or its role in modulating geochemical exchange between crust and
ocean.
Expedition 336 will initiate these investigations by
installing multilevel subseafloor borehole observatories (CORKs) at three sites
in a thinly-sedimented basin on the flank of the Mid-Atlantic Ridge called
North Pond. These North Pond CORK observatories will contain long-term coupled
microbiological, biogeochemical, and hydrological experiments. The basaltic
crust will also be characterized by coring parts of the crust, by collecting
downhole in situ petrophysical data by wireline logging, and by conducting
hydrologic (packer) experiments. Coring at four sites will characterize the
overlying sediment section.
The North Pond Expedition will lay the foundation for
long-term monitoring, experimentation, and observations by subsequent remotely
operated vehicle (ROV) or submersible dive expeditions. The installed CORKs
will be used in perturbation and monitoring points for single- and cross-hole
experiments.
Prior to Expedition 336, the JOIDES Resolution was berthed in Curaçao. Although the Expedition 336 officially did not begin until 15 September in Barbados, all of the CORK observatory hardware and experiments were sent to Curaçao in advance of the expedition. In addition, a few scientists and
engineers boarded the ship in Curaçao and used
the 2-day transit to Barbados to start preparing the CORK observatories and a
new in situ tool for detecting microbial life in ocean floor boreholes - the
Deep Exploration Biosphere Investigative tool (DEBI-t).
The remaining scientists,
engineers, and technical staff boarded the ship in Barbados on 16 September and
we left for the North Pond area on 17 September. During our first week on board
the ship, we have been conducting all the usual safety, science, and technical
orientation activities. However, our main focus has been to continue preparing
the scientific experiments to be deployed in the Hole 395A CORK observatory. This
includes all of the geochemical and microbiological experimental packages and
the pressure and temperature sensors and data loggers. The CORK engineers
prepared all the hardware and set up for deployment. CORK scientists and
engineers met to finalize the plan for our first observatory installation and
to pressure test the CORK plumbing.
After arriving on site and successfully
repairing the camera system winch, we were able to locate Hole 395A, lower the
CORK pulling tool over the existing CORK, and we successfully pulled the CORK
out of the hole. This CORK had been installed 14 years ago on ODP Leg 174B.
Once the CORK was secured on board, we pulled out the internal string composed
of a data logger, pressure sensors, and the 600 m long thermistor string that
was in open hole in the oceanic crust. The pressure and temperature data were
downloaded, the thermistors cut out of the string, and sections of the string
were sampled for microbiologic analyses. The last operation at the end of this
week consisted of preparing to trip back to the seafloor to log the hole with a
new in situ tool for detecting microbial life in ocean floor boreholes - the
Deep Exploration Biosphere Investigative tool (DEBI-t).
Operations
Week 1 of Expedition 336,
Mid-Atlantic Ridge Microbiology (North Pond), began with the first line ashore
in Bridgetown, Barbados at 0948 hours on 15 September 2011. Minor port call
activities began immediately after the early arrival. Airfreight shipments were
quickly loaded, completing all cargo operations immediately after arrival. On
day 2 of the port call, the science party and remaining technical staff joined
the vessel. Siem Offshore completed their scheduled crew change. The vessel was
then secured for sea and departed Bridgetown, Barbados at 0742 hours on 17
September 2011. The pilot departed the vessel at 0812 hours and the vessel
completed the 986 nm transit at 2330 hours on 20 September 2011,averaging 11.4
knots. At 0012 hours on 21 September 2011 the vessel was placed into dynamic
positioning mode and drill floor operations began. Prior to the start of CORK
pulling operations a planning meeting was held with Siem Offshore, IODP staff, the Chief Scientists, and other critical science staff.
Operations began at DSDP Hole 395A by first picking up the CORK
pulling tool for the Hole 395A CORK and making it up to a pony drill collar.
The rest of the bottom hole assembly (BHA) was attached and the drill string
was tripped to just above the seabed. At 2166 mbrf, tripping operations were
temporarily halted to install the VIT frame to begin running the subsea camera.
It quickly became apparent that there was a problem with the sonar system and
the VIT camera frame was pulled to repair the sonar. Tripping continued to 2824
mbrf where operations were again suspended to install the VIT camera frame.
Tripping operations resumed as the VIT was carefully lowered towards the
seafloor. Periodically the VIT winch was stopped and the hoisting function was
checked. At approximately 3700 mbrf, it became clear that the winch did not
have sufficient power to retrieve the VIT camera frame. Drill pipe tripping
operations continued while mechanics and engineers attempted to diagnose the
VIT winch problem. At 1630 hours tripping operations were complete and the top
drive was installed. From 1630 hours on 21 September 2011 until 1630 hours on
22 September diagnostics and repair were performed on the VIT subsea TV camera
winch. After changing both the hydraulic motor and the hydraulic pump the TV
camera winch was restored to a working condition. The VIT camera frame was
installed and lowered carefully to the survey position. The Hole 395A re-entry
cone and CORK were located and the pulling tool was lowered over the CORK at
2040 hours on 22 September 2011. The CORK was then picked up approximately 7 m
and the core line was deployed to retrieve the data logger through the drill
pipe. After running an overshot 3 times and attempting to jar onto the top of
the data logger, attempts to pull the thermistor string were halted and the CORK
was pulled to the surface. After landing and securing the CORK in the moon
pool, the recess where the top of the data logger was located was cleaned and
the overshot was installed. The data logger was then jarred loose and all 600
m, including 10 thermistors and sinker bar were removed at the rig floor. A
lifting sub was installed on top of the CORK and it was pulled through the rig
floor and then moved to the starboard aft main deck for sampling. Next the
stinger, made up of 3 joints of 5.5" drill pipe, was broken down and laid out.
After clearing the rig floor of CORK pulling tools, the logging bit and BHA
were made up and the drill string was tripped back to seafloor. There was a
break in tripping operations after running stand 70 to deploy the VIT camera,
which was lowered to the bottom, following the bit down. Hole 395A was
re-entered at 0134 hours on 24 September 2011 after a 19 minutes of maneuvering.
After rigging up to log with the DEBI-t microbiology string, it was run into
the hole to log Hole 395A. After a 45-minute interval to repair the logging
winch, the tools were run down into the hole. The logging tool was unable to
pass a section of the hole at 4670 mbrf (~186 mbsf) and after repeated attempts
the logging string was pulled back to surface and was rigged down at 1430
hours. We plan to lower the logging bit through this obstruction and then
re-deploy the DEBI-t logging string.
Education and Outreach
We have an active and wide-ranging education and outreach program
for our expedition. In addition to sailing with an Education Officer, two
videographers on board are filming an expedition documentary. Several shipboard
scientists are also leading interactive activities as well. These efforts are
focused through the JOIDES Resolution education web portal (www.joidesresolution.org)
and the Center for Dark Energy Biosphere (http://www.darkenergybiosphere.org/). Blogs are being posted there and in Scientific American (http://blogs.scientificamerican.com/expeditions/2011/08/30/introducing-expedition-336-at-north-pond/).
Interactive programs being conducted from the ship include live ship-to-shore interactions (40 currently scheduled), the "Adopt-A-Microbe" program (http://www.darkenergybiosphere.org/adoptamicrobe/), and "Classroom Connection," which is intended to spark interest and enthusiasm for learning in the special education classrooms (http://www.darkenergybiosphere.org/classroomconnection/).
On 19 September, scientists received an
orientation to education/outreach activities and opportunities to get involved.
The videographers have been busy throughout filming and interviewing for their
documentary. Our first live ship-to-shore interaction took place on 23 September
with high school juniors and seniors from Australia.
Technical Support and HSE Activities
Science Mission Support: Prior to the start of the
expedition supplies and equipment were loaded in Curaçao. After a two-day
transit, the ship arrived in Bridgetown, Barbados where the oncoming technical
staff completed crossover activities and the science party boarded the ship.
Starting in the port call and continuing on the transit to our first site,
oncoming scientists and engineers were introduced to their workspaces, met
technical staff, and trained on data systems and instrument hosts software.
Seafloor magnetic and bathymetric data were collected during our transit from
port call to our first site. On site, technical staff assisted microbiologists
with sampling and engineers with the retrieval of the thermistor string.
Other Technical Activities:
- Scientists involved in core description were introduced DESCLogik;
- NGR on site calibration was completed; work on the laser positioning upgrade was started;
- Technical staff assisted logging and CORK scientist position equipment and supplies in the lab;
- Additional counter space for the assembly of the osmotic samplers was installed;
- Work began on the rock saw splash hoods;
- The forward GPS antenna was installed;
- The Winfrog navigation system was reconfigured and following features implemented:
- The forward GPS was added as a secondary positioning input;
- Ship's heading can now use either the ship's gyro or use the base line calculations between the two GPS antennas;
- Work began on 3D camera testing;
- Issues with RF noise disrupting the PWL velocity signal were resolved by shielding the track's servo motor and adjusting equipment grounding;
- X-Bob wireline depth display problems continues to be diagnosed
The
science party and new technical staff completed Siem Offshore's safety
induction and the IODP's Laboratory Safety Tour. The weekly fire and abandon
ship drill was held as scheduled. In addition, safety training was given to
scientists needing to work periodically on the rig floor.
|