Next week >
IODP Expedition 340: Lesser Antilles Volcanism and Landslides
Week 1 Report (3-11 March 2012)
PDF file is available for download.
Operations
Week 1 of Expedition 340 began while
sitting alongside the Navy Frontier Pier in San Juan, Puerto Rico. The vessel
was secured for sea with final maintenance checks performed prior to departure.
Last line was released from shore at 08:48 beginning the passage to Site U1393
(CARI-02C). After a 347 nautical mile transit from San Juan, Puerto Rico to
Site U1393 (CARI-02C), which included an unplanned diversion to a rendezvous
point, just off the coast of Antigua, to pick up a Siem Offshore crew member,
the vessel arrived at the first expedition location, Site U1393 (CARI-02C). The
vessel stabilized over Site U1393 (CARI-02C) at 18:00 on 6 March.
The BHA was picked up and drifted,
followed by running drill pipe to bottom. Prior to starting coring operations a
seafloor survey was conducted to locate favorable locations to spud possible
holes at the site. A clockwise spiral on a 20-m center was conducted. The
survey identified a large megablock to the southeast
of the preliminary location and our first hole was adjusted to 20 m west of the
original location. A single hole was then cored at this site to a depth of
47.55 mbsf with an 11 7/16" diameter APC/XCB core bit and
a 135.75 m long BHA. A mud line core with the APC system established a water
depth of 926 mbsl. The second APC core bounced off the formation and the APC
system was changed over to the XCB coring system. Coring conditions proved to be very difficult
and recovery was very poor. Coring was terminated at 05:15 on 8 March when the
XCB system failed, leaving part of the XCB core barrel in the hole. The
remainder of the XCB system was retrieved by wireline. The drill string was
then pulled clear of the seafloor, the top drive was set back and the drill
string was tripped to surface while the vessel began its 5.3 nm transit to Site
U1394 (CARI-03C). At 10:25 on 8 March the bit cleared the rotary table ending
Hole U1393A. Overall core recovery for Site U1393 was 11.4% of the 47.5 m cored. Core recovery for the two APC cores was 4.36 meters for
the 4.4 m advance. An additional 5 XCB cores were attempted over a depth of
43.1 m with only 1.05 m of core recovered. Most of the recovery consisted of
small diameter pieces of volcanic debris. Two holes were originally planned for
this site, but because of the poor drilling conditions, the second hole was
cancelled.
After inspecting the APC/XCB BHA for
damage, 6 additional drill collars were picked up and the BHA and drill pipe
were tripped into the hole. The
vessel arrived at Site U1394 (CARI-03C) and was in position at 12:30. Because a
subsea communications cable had been run in the general area of operations a
camera survey was performed to make certain that our operations would not
impact the cable. At 16:30 the
bottom survey began at the preliminary site coordinates. A 40 m square survey was conducted with no signs of a subsea cable. The
seafloor was tagged twice during the survey to establish depth from the drill
floor. Tagged depth at both locations was 1126.6 mbrf. After
the survey was completed, the VIT was removed, the top drive was picked up and
the bit was spaced out to spud Hole U1394A. Hole U1394 A was spudded at 19:45 on 8 March. The seafloor depth was calculated from the length of the first core to be 1126.3 mbrf. APC refusal on Hole U1394A came on the
fourth piston core at a depth of 23.9 mbsf. The XCB system was then deployed and
coring continued through Core U1394A-27X without problems, but with generally
poor recovery.
Just after midnight on 10 March while
retrieving XCB Core U1394A-28X, the wireline overshot detached from the XCB
barrel. The sinker bar assembly was pulled to the surface, drill string
connection opened and wireline sinker bar assembly inspected to determine where
the overshot assembly parted. Two unsuccessful attempts were made to retrieve
the lost core barrel. When the mud pumps were engaged again after tightening
the pipe connection, the drill string was packed off and bled off. Shortly
thereafter drill string rotation was lost Attempts were made to regain rotation
and circulation for ~3.5 hours, and the decision was made to call out the
Schlumberger Engineer to begin preparations to sever the drill string just below
the upper connection on the tapered drill collar (TDC).
While the Schlumberger Wireline
engineer made the necessary checks of the severing equipment, a Bowen wireline
fishing overshot was deployed in two unsuccessful attempts to grab the overshot
outer body. The drill sting was severed at 14:20 on 10 March at ~1240 mbrf, just below the upper connection of the TDC. All of
the BHA components below the 5.5" transition pipe were left in the hole along
with the XCB core barrel and Core U1394A-28X.
Schlumberger severing equipment was
then rigged down and the wireline pulled back to surface. The remainder of the
drill string was tripped to the surface and the severed end of the TDC cleared
the rotary table at 18:45 hours on 10 March.
A new bit and BHA were then picked up,
drifted, measured and deployed for Hole U1394B. At midnight on 10 March drill pipe was being run into the hole at a depth of 126 mbrf.
Science Results
The aim of IODP
Expedition 340 is to understand the constructive and destructive
processes related to volcanism along island arcs. Processes occurring along
these arcs are among the most fundamental ones occurring on our Earth, as
roughly 50% of volcanism along the circum-Pacific
ring of fire is associated with island arcs. Nonetheless, several aspects of
this type of volcanism, such as the processes controlling the changes and the
diversity in magmatism and eruptive activity on individual islands as well as
along an arc or the emplacement processes of large debris avalanches, are not well
constrained. The identification of the controlling mechanisms of these
processes is essential because of their potential association with large
geohazards (explosive eruptions, tsunamis). Generally, the cores and logging
data retrieved during this expedition will be used to investigate the magmatic
evolution and the eruptive activity in space and time along the Lesser Antilles
Arc as well as on the identification of the mechanisms controlling triggering,
transport, and deposition of volcanic debris avalanches, including an
assessment of volcanic hazards being potentially coupled with the eruptive
processes and debris avalanche emplacement.
The scientific party arrived on board
the JOIDES Resolution on 3 March.
They spent the first three days of the expedition familiarizing themselves with
the laboratories, instrumentation, documenting methods, and practicing core
flow and sampling procedures. They also received a comprehensive training on
DESClogik, the application for entering descriptive data into the database. The
respective templates for the descriptive groups have also been finalized during
this period. In addition, shipboard sampling strategies and core flow were
discussed. By the end of this week, all groups submitted their first draft of
the ÒMethods" chapter (explanatory notes) for the Expedition Reports. A
coordinated shipboard sampling plan was developed and agreed upon. All personal
sampling, except for microbiology, pore water and geotechnical testing, will happen during a postcruise sampling party in College Station, Texas.
During this week we started and
finished coring operations at Site U1393 (CARI-2C), started and finished coring
operations in Hole U1394 (CARI-3C) and started coring operations in Hole U1394B.
Site U1393 was designed to retrieve as much material as possible of the
youngest debris avalanche deposit (deposit 1) created by the Soufrière-Hills volcano on Montserrat. Drilling in this
unconsolidated, heterogeneous, chaotic material was extremely difficult and we
only retrieved at total of 5.42 m of material. The bottom depth at this site is
48 mbsf. The upper ~4 m of material retrieved at Site U1393 consist of mud
clasts being distributed in a sandy matrix followed by a mixture of dark
brownish gray-black volcaniclastic sand with medium to very coarse sand-sized
grains of andesitic lava and carbonate material. Below this only cut up
pieces of andesite, sometimes hydrothermally altered or oxidized, were
occasionally retrieved within the core catcher. Site U1394 was designed to core the distal parts of an older debris
avalanche deposit (deposit 2) of the Soufrière-Hills
volcano on Montserrat and to reach the interface between the base of the debris
deposit and the underlying sediment. We recovered at total of 57 m of material
with an average recovery rate of 23% from Hole U1394A. The total depth reached
into the formation was 254 mbsf. As planned, we reached the interface region
between the debris avalanche deposits and the underlying marine sediment but
also recovered material of an even older debris avalanche deposit below it. The
upper parts of the recovered material consist of volcaniclastic sediments
followed by a mix of volcano clastic and biogenic sediments, followed by
turbidites composed of volcanic material with basaltic fall out deposits at the
base. Below this package material of the debris avalanche deposit was
retrieved. Beneath these deposits mainly hemiplegic sediments have been cored.
From the base of this hole we retrieved andesitic fragments of an older debris
avalanche deposit.
Education and Outreach
The expedition education officer has
already been very active. After giving the scientists a presentation on the
general program she started blogging and posting pictures. We also had the
first live ship to shore videoconferences with different groups during this
last week.
Technical Support and HSE Activities
Science Mission Support:
Technical staff completed crossover and port call logistics activities in San
Juan, Puerto Rico. The Science Party members were introduced to their laboratories, met technical staff, and trained on data systems and instrument host software. Upon
arrival at our first site, the technical staff has been fully engaged in
providing full support for coring operations and preparing seismic equipment
for a possible vertical seismic operation.
Other Technical Activities:
Work continues on the Cold Laboratory ceiling after parts arrived in port call.
The
remaining fancoils have been installed in the Core Storage Area and electrical
wiring started for power and control started.
Testing of the laser engraver is in progress.
HSE Activities:
The science party and
new technical staff completed Siems's safety induction and the IODP's Laboratory
Safety Tour. The weekly fire and abandon ship drill was held as scheduled.
|