Table T2. Operations summary and time estimates for Expedition 305.
Ponta Delgada, Azores
3.7
AMFW-01A
30.170°N,
42.123°W
1630
Hole A: Bare rock spud, RCB 4.5 m cores 0130 mbsf (3.1 days)
Drop bit, log: triple combo, FMS/sonic, UBI (1.2 days)
Hole B: HRRS hammer drill-in 22 m of 133/8 inch casing (1.9 days)
Underream 143/4 inch hole with bicenter bit to ~130 mbsf (3.1 days)
Run 120 m of 103/4 inch casing with MM and underreamer (1.7 days)
Set retainer, cement 103/4 inch casing (0.9 days)
Clean out cement, RCB 4.5 m cores 130250 mbsf
4.2
RCB 4.5 m cores 250370 mbsf
4.1
RCB 4.5 m cores 370490 mbsf
3.8
RCB 4.5 m cores 490610 mbsf
4.3
RCB 4.5 m cores 610730 mbsf
4.4
RCB 4.5 m cores 730850 mbsf
4.4
RCB 4.5 m cores 850970 mbsf
4.5
RCB 4.5 m cores 9701090 mbsf
4.7
RCB 4.5 m cores 10901100 mbsf
1.6
Log: triple combo, FMS/sonic, magnetometer, UBI
2.5
Vertical seismic profile
Subtotal = 36.0 days
0.5
Hole B: RCB 4.5 m cores 0 to ~26 mbsf
Subtotal = 1.6 days
1.6
Ponta Delgada, Azores
3.7
7.4
37.6
3.0
AMFW-01A
~30.17°N,
~42.12°W
1630
HRRS hammer drill-in 22 m of 133/8 inch casing
1.9
Underream 143/4 inch hole with bicenter bit to ~130 mbsf
3.1
Run 120 m of 103/4 inch casing with MM and underreamer
1.7
Run retainer, cement 103/4 inch casing
0.9
Clean out cement, RCB 130250 mbsf
3.8
RCB 250370 mbsf
3.8
RCB 370490 mbsf
3.8
RCB 490610 mbsf
3.9
RCB 610730 mbsf
4.0
RCB 730850 mbsf
Subtotal = 31.0 days
4.1
Drop bit; log: triple combo, FMS/sonic, magnetometer, UBI
2.5
Vertical seismic profile
Subtotal = 3.0 days
0.5
Footwall
peridotite
~30.17°N,
~42.12°W
1630
RCB to bit destruction
35
Footwall
peridotite
~30.17°N,
~42.12°W
1630
MDCB core 4.5 mbsf
1.8
AMHW-01A
~30.19°N,
~42.07°W
2580
RAB to bit destruction
3.0
See additional alternate sites in Table T1.
Note: RCB = rotary core barrel, FMS = Formation MicroScanner, UBI = ultrasonic borehole imager, HRRS = hard rock reentry system, MM = mud motor, MDCB = motor-driven core barrel, RAB = resistivity at the bit.