Sites
U1403 |
U1404 |
U1405 |
U1406 |
U1407 |
U1408 |
U1409 |
U1410 |
U1411
IODP Expedition 342: Paleogene Newfoundland Sediment Drifts
Site U1402 Summary
PDF file is available for download.
Background and objectives
The Motion Decoupled Hydraulic Delivery System (MDHDS) is
an engineering development intended to serve as a foundation for future
penetrometer and other downhole tool formation measurements. The MDHDS is designed so that downhole
tools that are in the formation can be driven into the formation hydraulically
and decoupled from the heave of the drill string, which negatively impacts
these measurements.
The plan for the sea trial of the MDHDS was to carry out two tests of the tool set in the water
column, wash to 100 m below seafloor (mbsf), test the MDHDS in situ for at
least 30 minutes, turn on the pumps to clean the hole, take an APC core, test
the tool in situ again, and take three more APC cores. The site chosen for the
tests was a reoccupation of ODP Site 1073, New Jersey Margin.
Principal Results
After
a 582 nmi transit from Bermuda to Site U1402 (ODP Site
1073), the vessel arrived at the first expedition location to perform
engineering qualification tests on the MDHDS. The vessel was on Site U1402 at
1542 h (UTC-3h) on 6 June 2012. Two holes ended up being drilled at IODP Site
U1402. Hole U1403A was drilled without coring to 96.4 m to perform MDHDS testing. Hole U1403B was drilled to 15.03 m CSF to obtain two cores, test laboratory equipment and provide experience for the science staff.
The
drill pipe was lowered to 608 m below rigfloor (mbrf) and the MDHDS with the Temperature and Pressure (T2P)
tool were made up for deployment using the developmental electronic release
system (ERS) tool on the Schlumberger wireline. After running the tools through
the blocks, a surface test was performed to check all components prior to
deployment. A communication problem with the tool was fixed and the
Schlumberger wireline was run into the drill pipe to ~250 mbrf, where the ERS
released prematurely, allowing the MDHDS and T2P to fall 400 m to the landing
seat in the Bottom Hole Assembly (BHA). An attempt was made to re-latch the ERS
tool to the MDHDS without success and the Schlumberger wireline was pulled from
the drill pipe. An MDHDS mechanical latch assembly with sinker bars was
assembled and deployed on the coring line in an attempt to fish the MDHDS tool,
but this did not work. Upon retrieval of the coring line, the sinker bars were
observed to have parted from the retrieval sub (RS) overshot, leaving a
configuration that was impossible to fish. The decision was made to pull the
drill string out of the hole to retrieve the test equipment inside the BHA.
After
tripping out of the hole, the test equipment was removed from the BHA, and
inspected for damage. It was found that the ERS was in the unlatched position.
This may have caused the tool to drop in the first place and may have been the
reason the MDHDS could not be retrieved with the ERS. The drill string was
again deployed and Hole U1402A was spudded at 1405 h on 7 June, with the
seafloor recorded at 650 mbrf. Hole U1402A was washed down to 96.4 m (746.4
mbrf) and the MDHDS, T2P and ERS were assembled and deployed for a second test.
The MDHDS was lowered by the ERS to the BHA at 96.4 mbsf. The ERS was unlatched
with the tether system and raised two meters above the BHA. The drill string
pressure was raised and the T2P penetrometer was successfully deployed into the
formation. Temperature and pressure signals were successfully transmitted to
the rig floor for 30 minutes and recorded downhole. When circulation was
re-established to clear the BHA of settled sediment, telemetry was lost. The
ERS was then lowered and re-latched into the MDHDS. However, it was found that
the MDHDS could not be retrieved with the wireline system. The wireline tension
was increased to ~8,000 lbs. It was interpreted that the MDHDS had jammed in
the BHA. The ERS was released and the Schlumberger wireline was pulled from the
hole, the top drive was set back and the drill string was tripped from the
hole. The bit cleared the rotary table at 0110 h ending Hole U1402A. It was
found that the tether within the MDHDS had been worked between the tool and the
inside of the BHA aperture, jamming the tool in place and preventing recovery. There was also significant sediment within the BHA. This concluded the MDHDS sea
trial.
The
ERS and the MDHDS worked well in this second deployment. The in-situ pressure
was successfully measured and equal to 7.536 MPa, just slightly above
hydrostatic pressure. The MDHDS was successfully delivered to the BHA and released
with the ERS. In addition, the inner MDHDS subassembly was successfully
unlatched from the outer subassembly and the T2P was driven into the formation
with no damage to the penetrometer tip. Analysis of accelerometer and pressure
data showed no coupling with the drill string. While real-time data were acquired
through the tethered system, problems with the tether associated with drill
string pressurization suggest that this component (real time telemetry with a
tether) is not ready for regular shipboard use.
When
the MDHDS tests were concluded, several hours remained until a helicopter would
arrive to exchange departing engineers with arriving science support
technicians. The science party requested that a few cores be obtained from Site
U1402 to test lab equipment and provide experience for the science staff. The
vessel was offset 20 m to the east, the drill string was deployed a third time,
and Hole U1402B was spudded at 0625 h on 8 June. Two cores were taken from 0-15
mbsf, with 100% recovery. Core U1402-1H was a 7-m long mudline core, and Core
U1402B-2H was an 8-m long partial stroke core that suffered significant core
liner damage.
While
working on retrieving the second core a scheduled helicopter arrived at 0932 h
with four USIO staff. The helicopter refueled, took on five MDHDS
scientists/engineers and luggage and departed the JOIDES Resolution at 1020 h. The rig floor was secured at 1330 h on
8 June, ending Hole U1402B, and the vessel was underway at full speed to Site
1403 (proposed site JA-1A).
Analysis
of Cores U1402-1H and 2H showed the sediment to be unconsolidated, sticky, grey to dark grey-brown Pleistocene-Holocene silty mudstone.
The mud contains abundant woody organic matter and patches of sulfides as well
as mollusk shell fragments. The sediment is similar to pro-glacial muds
elsewhere along the continental margin. The microfossil assemblage consists of
sponge and diatom fragments, a foraminifer assemblage dominated by benthic
species, and a late Pleistocene calcareous nannoplankton assemblage. Both the
benthic foraminifer and calcareous nannoplankton assemblages include, in
addition to Pleistocene species, a mixed reworked assemblage. For example,
reworked calcareous nannoplankton includes markers for the lower Oligocene, the
upper Eocene, and the Cretaceous. Planktonic foraminifers are dominated by cold
water Pleistocene species. Benthic foraminifers are typical of slope water
depths of 400-600 m. Section U1402B-1H-1 has normal magnetic polarity and a
short reversed interval was detected in Section U1402B-1H-3. A similar reversal
event was reported at 14.8-15.7 mbsf at Site 1073 and was provisionally
identified as the Laschamp or Blake excursion. Nannofossil biostratigraphy
indicates that the base of Hole U1402B cannot be older than 70 ky, so we
interpret the reversal at 6.15-6.20 m to be the ~38-40 ky Laschamp excursion.
|